The much awaited state-of-the-art Tsabong multi species abattoir is taking shape.
The P161 million project, which was scheduled to be completed in October this year, has been rescheduled for completion in April 2023 due to unforeseen circumstances.
Speaking during Kgalagadi District full council meeting on Monday, council chairperson Mr Hendrick Jacobs said the overall work as at 28th October 2022 was at 70 percent.
He attributed delay to various issues such as variations of electrical components and delay in supply of steel. Construction is progressing well on other aspects and the contractor is currently working on construction of the abattoir access road. ends